SERVICES
OUR ACTIVITY
With a very wide base of Clients, mainly in the Industrial area, we dedicate ourselves to a variety of activities that place us in a privileged position, due to the broad knowledge accumulated over the years, namely in electricity, instrumentation and automation.
Thus, we have the know-how to face the most challenging challenges;
- Electrical and automation projects;
- New assemblies or maintenance in the Industrial area, namely in the field of Electricity and Instrumentation;
- Repairs and calibrations of all type of instrumentation equipment, such as the opening, repair and calibration of automatic valves or On-Off of all brands in the market. We are also able to work on any type of transmitters, including “new generation;
- Execution of Medium Voltage projects, namely new assemblies or maintenance
- Project and implement Fire Detection, Fire Extinguishing, CCTV Surveillance, anti-intrusion, etc.
RELEVANT WORKS
– Electrical and Instrumentation Installation of a 37MW turbo generator at Europac Viana
– Electrical installation, low and medium voltage, telephone, fire detection and extinguishing, sound and ventilation, in the Senior Rest Club “Casa dos Leões” in Carnaxide
– Installation of new paper winding machine in Renova
– Electrical and instrumentation installation, in the fuel park of Faial, Azores, including automation project
– Installation of the new electro filter in The Navigator Company, Setúbal.
– Electrical installation of the new Lusosider pickling machine
– Installation of the Coal Hangar, the Waste System and Expedition System I, Grapnel Sea, at Secil Outão
– Installation of the acid system automation in the Cellulose do Caima
– Recovery of all Electrical and Instrumentation Installation, with opening, repair, improvement and calibration of all the instruments, related to the boilers SG4001 A and SG4001 D of GALP Energy, in Leça da Palmeira
– Electrical Installation BT, MT, HVAC and Instrumentation of the new WWTP at Europac Viana
– Electrical and Lighting Installation in the North Extension of Building 2 of Volkswagen Autoeuropa
– Electrical and Instrumentation Installation of two new Presses in The Navigator Company Setúbal
– Modification of the transport and automation system in the transport lines of car bodies for painting at Volkswagen Autoeuropa
– Electric installation of new system for logs receiving , shredding,conveyors and storage of shard, in Celtejo
– Implementation of Electrical Installation, Instrumentation and Automation, of the new Paper Machine and Rewinder of Fapajal
– Electrical installation of new system of Receiving Shredders, Conveyors and Storage, in CELBI
– Execution of the Fire Detection Facility at the Ribeira Grande Geothermal Power Plant in the Azores
– Alteration of the automation in the lines of the Conveyors of Sharan NF, Volkswagen Autoeuropa
– Execution of the Electrical Installation and Instrumentation of the new Copper Washing Line RC, at Somincor
– Supply and assembly of the MCC’s of the new Copper Washing in Somincor
– Electrical and Instrumentation Installation of Turbo Rolls Royce Generator at Europac Viana
– Installation of Transformers, Medium and Low Voltage Switchgear, installation of Instrumentation for the new Cogeneration Boiler at Europac Viana
– Supply and assembly of Plant Plant MCCs at Somincor
– Installation of Oil Fuel Pumping at Belo Jardim Thermal Power Plant, Terceira Island, Azores
– Execution of the Installation of the Photovoltaic Park of Castanhos, Mértola
– Electrical Installation of Zinc Lavatory Dosing Pumps at Somincor
– Installation of DAISA Line Feed at Lusosider
– Assembly of the Pulp Expert DCD unit in Cellulose do Caima
– Supply and assembly of the MCC’s of the ETAM in Somincor
– Installation of network analysers to optimize the consumption and analysers of chimney gases in Repsol, Banática
– Supply and assembly of the MCC’s of the new Zinc Washing in Somincor
– Up Grid Flotation of Copper Washing at Somincor
– Enlargement of the Zinc Wash – Somincor
– Installation of Alcont System of Digestor 1 and 2 in The Navigator Company Setúbal
– Volkswagen Autoeuropa Tool & Die II Power Increase
– Installation of Auxiliary Boiler on Celtejo
– Execution of feeds to the 3rd production line of The Navigator Company Vila Velha de Ródão
– Maintenance of the Thermoelectric Power Plant of Belo Jardim, Terceira Island, Azores
– Modification of the installation of the Mitsubishi- Benz Paint zone in Tramagal
– Replacement of the air carrier for the port dock of Somincor Setúbal
– Electrical and Instrumentation Installation of New Press S711 in The Navigator Company Setúbal
– Execution of the battery charging room in Volkswagen Autoeuropa
– Electrical installation of the Extension Buildings of Canopy G, Building 2 and Logistics in Volkswagen Autoeuropa
– Electrical and instrumentation installation of the Hydrogen Network at Solvay
– The Navigator Company Cacia Cal Furnace Natural Gas and Instrumentation Installation
– Installation of the new Turbo Blower at The Navigator Company Figueira da Foz
– Execution of design and electrical installation and instrumentation in the Central of Storage and Preparation of Cal in Somincor
– Electrical installation and instrumentation in the new SVP filter of The Navigator Company Setúbal
– Execution of design and electrical installation and instrumentation in the Industrial Water Tanks TAI at Somincor
– Electrical installation of the Bicolour Painting Building at Volkswagen Autoeuropa
– Electrical installation of the Robotization of the Double Color line in Volkswagen Autoeuropa
– Electrical and instrumentation installation to increase the production capacity of the Paper Machine at Europac Viana
– Electrical and automation renewal of TAP4 at Volkswagen Autoeuropa
– Execution of electrical installation and instrumentation in the Industrial Water Treatment FHDS / Osmosis in Somincor
Electrical installation of the enlargement of the Logistics-Painting Building in Volkswagen Autoeuropa
– Execution of electrical installation and instrumentation of Water Lines Copper Washing at Somincor
– Electrical and instrumentation installation of Lallemand’s new production line
– Electrical installation and fire detection of the new Celtejo Steam Turbine Building
– Improvement of transport guides on Machine 502 in Amarsul
– Implementation of the reallocation of the power cables in the ZEP in Somincor
– Electrical installation of Audit and Stamping rooms at Volkswagen Autoeuropa
– Execution of power supply to the CPV21 and CPV23 of the ZEP at Somincor
– Execution of the electrical implementation of the Expander Project in Sovena
– Execution of the MCC’s supply to the ZEP at Somincor